The Town of The Blue Mountains would like to notify the public that Staff Report OPS.25.015 was added to the Revised Agenda for the Committee of the Whole meeting scheduled for Tuesday, March 18. The report provides an update on the staging site for the construction of the new Thornbury Wastewater Treatment Plant Outfall pipe.
Lora Bay Park has been selected as the site for the staging and assembly of the new outfall. The outfall will be assembled in segments, and then towed across Georgian Bay for installation north of the Grey Street road allowance in Thornbury. The report includes a communications plan, along with a set of Frequently Asked Questions covering how Lora Bay Park was selected and how the public will be impacted.
Contractors are expected to be on site at Lora Bay Park on Tuesday, March 18, to begin topographical surveying. This information will be used to assist with the development of a site plan for the future construction work.
For more information, please contact:
Town of The Blue Mountains
Manager of Water & Wastewater
(519) 599-3131 ext. 226